Official: Solar project design flaws and site changes led to millions in cost overruns

Two of the professionals who advised on an $88-million solar project in three counties - and who also helped construct the subsequent $21-million public bailout of the project - have resigned, Morris County says. (Courtesy of SunLight General)

MORRIS COUNTY — Design drawings that had to be changed, construction that had to be redone and the changing of sites contributed to cost overruns that led to lawsuits resulting in a $66.3 million arbitration award in a three-county solar project that fizzled, according to a report by the project’s construction adminstrator. The cost overruns were…